How many forklifts a shift needs
Pallet moves per shift, the cycle time, hours, and utilization in; the trucks needed and the moves each one makes.
Read the guide: what the number means and how to use it
- Truck-minutes of work = moves × cycle time. Available minutes per truck = shift hours × 60 × productive fraction. Trucks = work ÷ available, rounded up, plus spares.
Need it quoted?
Guardrail, bollards, rack protection, and mezzanines priced as line items.
Guardrail and protectionForklift fleet size
Trucks to run
8
7 working + 1 spare
Working trucks
7
Moves per truck per shift
86
- Truck-hours of work
- 40 h
- Utilization of the working trucks
- 71 %
One line for the file or the vendor
600 moves x 4 min over 8 h at 0.75 productive: 7 working trucks + 1 spare, 86 moves each.
How it is figured
- Truck-minutes of work = moves × cycle time. Available minutes per truck = shift hours × 60 × productive fraction. Trucks = work ÷ available, rounded up, plus spares.
Sources: Warehouse engineering practice (time standards and fleet sizing); MHI. A planning calculator; the maker, the engineer of record, or the code official confirms the final number.
Questions people ask
- How do I get the cycle time?
- Time 20 or 30 moves of each kind with a stopwatch or pull them from the WMS task timestamps, and weight them by how many of each kind the shift does. Travel distance dominates, which is why slotting fast movers near the dock cuts the fleet.
Related calculators: Conveyor throughput, Dock doors needed, Forklift aisle width. All calculators.