Concrete yardage: the guide
Concrete is bought by the yard, and the slab, the footings, and the ramp are three volumes added together with waste on top and rounded up to the truck.
Why this number matters
Length times width times thickness in feet, over 27, is cubic yards; a 100 by 60 slab at 6 inches is 111 yards. Footings are width times depth times the length of the run, a ramp is a wedge whose average thickness is half the rise plus the slab it sits on, and waste covers the base that was not quite level, the form that bowed, and the last truck's partial load. Eight to ten percent is usual for a slab; pours with many thickened edges run more.
Trucks carry about 10 yards, and short loads cost extra, so the order is rounded to the half yard and the count of trucks tells you how the pour day will run. A warehouse slab is usually 6 inches of 4,000 psi concrete on compacted base, 7 or 8 where rack post loads or heavy trucks say so, and the thickness, the joints, and the reinforcing are the engineer's call.
The related calculators show where the thickness comes from: the rack post and mezzanine column loads that land on the slab.
How it is figured
- Volume in cubic feet ÷ 27 = cubic yards. Slab: length × width × thickness. Footing: width × depth × length. Ramp: length × width × (half the rise + the slab thickness), a wedge on a slab.
A worked example
A 100 by 60 slab at 6 inches is 111.1 yards, a 24 by 12 inch footing around the 320-foot perimeter is 23.7, and with 8% waste the order is 145.5 yards, 15 trucks.
The tool's starting values, and what it returns for them:
| Slab length | 100 ft |
| Slab width | 60 ft |
| Slab thickness | 6 in |
| Footing width | 24 in |
| Footing depth | 12 in |
| Footing length | 320 ft |
| Ramp length | 0 ft |
| Ramp width | 12 ft |
| Ramp rise | 48 in |
| Waste | 8 % |
| Order | 146 cu yd |
| Truckloads | 15 |
| Slab | 111.1 cu yd |
| Footings | 23.7 cu yd |
| Ramp | 0 cu yd |
| Slab area | 6,000 sq ft |
Mistakes that catch people
- Dividing by 27 with the thickness still in inches.
- No waste on a slab over an uneven base; the first inch of over-excavation across the whole floor is a truck.
- Forgetting the thickened edges, pits, and curbs.
Rules of thumb
- A 4-inch slab is 1 yard per 81 square feet; 6 inches, 1 per 54; 8 inches, 1 per 40.
- 8 to 10% waste; 10 yards a truck.
- Dock leveler pits are a subtraction and the pit walls an addition; get the pit drawing.
When to stop calculating and make a call
- Slab thickness, reinforcing, joints, and subgrade for a warehouse: a geotechnical report and a structural engineer.
- Large pours: the ready-mix supplier's scheduling and the finisher's crew size set the day.
Questions people ask
- How thick should a warehouse slab be?
- Six inches of 4,000 psi concrete carries most forklift and rack loads on a prepared base; heavy rack post loads, wide trucks, or poor soil push it to 7 or 8 inches, and the rack maker's post loads should be checked against the slab by an engineer.
Standards and sources
- Geometry; ACI 302.1R for slab practice
This guide and the tool are planning aids. The equipment maker, the engineer of record, the accountant, or the code official confirms the final number for your building.