Concrete for a slab, footings, and a ramp
Slab size and thickness, footing size and run, and a ramp if there is one in; the cubic yards for each, the waste, and the truckloads.
Read the guide: what the number means and how to use it
- Volume in cubic feet ÷ 27 = cubic yards. Slab: length × width × thickness. Footing: width × depth × length. Ramp: length × width × (half the rise + the slab thickness), a wedge on a slab.
Need it quoted?
Send the footprint, eave height, and openings and the quotation comes back with frames, sheeting, trim, insulation, and doors as line items.
Metal buildingsConcrete yardage
Order
146 cu yd
134.8 + 8% waste
Truckloads
15
at 10 yards a truck
Slab
111.1 cu yd
- Footings
- 23.7 cu yd
- Ramp
- 0 cu yd
- Slab area
- 6,000 sq ft
One line for the file or the vendor
Slab 100x60 ft at 6": 111.1 yd; footing 24x12" x 320 ft: 23.7 yd; ramp 0 yd; order 146 yd (8% waste), 15 trucks.
How it is figured
- Volume in cubic feet ÷ 27 = cubic yards. Slab: length × width × thickness. Footing: width × depth × length. Ramp: length × width × (half the rise + the slab thickness), a wedge on a slab.
Sources: Geometry; ACI 302.1R for slab practice. A planning calculator; the maker, the engineer of record, or the code official confirms the final number.
Questions people ask
- How thick should a warehouse slab be?
- Six inches of 4,000 psi concrete carries most forklift and rack loads on a prepared base; heavy rack post loads, wide trucks, or poor soil push it to 7 or 8 inches, and the rack maker's post loads should be checked against the slab by an engineer.