Efficiency and labor · guide
Labor productivity: the guide
Units per labor hour is the one warehouse number that ties the schedule, the headcount, and the cost per unit together, and the gap to a target is worth a known number of dollars a year.
Why this number matters
Divide what a shift handled, cases picked, pallets moved, lines shipped, by the labor hours it took and you have the rate; multiply the hours by the loaded wage and divide by the units and you have the cost per unit, the number the customer quote is built on. Against a target, the engineered standard or the best shift on record, the gap is hours, and hours times wage times shifts is what closing it is worth, which is the budget for the fix: slotting, a better pick path, a conveyor, a second pallet jack.
The rate depends entirely on the work, and the benchmarks that get quoted, 60 to 100 cases an hour from pallet rack, 150 to 250 lines in a pick module, 20 to 30 pallets an hour on a forklift, are only useful next to your own best. Measuring every shift the same way matters more than the standard; a drop of 10% in a week is a problem to find before it is a number to explain.
The loaded wage is the base rate times 1.3 to 1.4 for taxes, benefits, and insurance; using the base rate understates the value of every hour saved by a third.
How it is figured
- Units per labor hour = units ÷ (people × hours). Cost per unit = labor hours × loaded wage ÷ units. Hours at target = units ÷ target rate; the difference times the wage times the shifts is what the gap costs a year.
A worked example
Twelve people on eight hours handling 6,400 units is 66.7 units per labor hour at $0.42 of labor each; against an 80 target that is 83%, 16 labor hours a shift, two people's worth, and $112,000 a year at $28 loaded.
The tool's starting values, and what it returns for them:
| Units handled per shift | 6,400 |
| People on the work | 12 |
| Hours each per shift | 8 h |
| Loaded wage | 28 $ per hour |
| Target rate | 80 units per labor hour |
| Shifts per year | 250 |
| Units per labor hour | 66.7 |
| Labor cost per unit | 0.42 $ |
| Against the target | 83 % |
| Labor hours per shift at the target rate | 16 h |
| Yearly value of reaching the target | 112,000 $ |
| Labor cost per shift | 2,688 $ |
Mistakes that catch people
- Counting only the pickers' hours and leaving out the lead, the replenisher, and the checker.
- A target from an industry article for work that is not the same work.
- Measuring units that are not the same size: a case and a pallet are different units.
Rules of thumb
- Loaded wage = base × 1.3 to 1.4.
- Your best shift is the honest target until a standard exists.
- A 10% drop in a week is a question for that week.
When to stop calculating and make a call
- Engineered labor standards and incentive pay: an industrial engineer and the labor agreement.
- Automation justifications: the ROI calculator with these hours as the saving.
Questions people ask
- What is a normal pick rate?
- It depends entirely on the work: 60 to 100 cases an hour for case picking from pallet rack, 150 to 250 lines an hour for each-picking in a good pick module, 20 to 30 pallets an hour on a forklift between dock and rack. Your own best shift is the honest target until an engineer sets a standard.
Standards and sources
- WERC DC Measures (warehouse productivity benchmarks)
- Industrial engineering time standards practice
This guide and the tool are planning aids. The equipment maker, the engineer of record, the accountant, or the code official confirms the final number for your building.