Branch circuits for an in-plant office

Receptacles, lighting, HVAC, and equipment in; the 20 A circuits, the panel size, and the feeder to the office.

Read the guide: what the number means and how to use it

  • Receptacles at 180 VA each (NEC 220.14(I)) on 20 A circuits loaded to 80% (1,920 VA); lighting at 125% continuous; HVAC at about 1,200 VA per ton plus electric heat, at 125%; dedicated equipment at 1,500 VA each.
  • Feeder amps = total VA ÷ (volts × 1.732 for three phase); breaker at 125% rounded up to a standard size. Panel spaces with about 30% spare.

Need it quoted?

In-plant offices sized to the headcount, pre-wired, with HVAC and restrooms, priced as line items.

Modular offices

Office circuits and panel

20 A circuits5feeder amps60

20 A circuits

5

2 receptacle + 1 lighting + 2 dedicated

Feeder breaker

60 A

44 A load at 208 V 3-phase

Subpanel

12-space, 100 A

Connected load
15,880 VA
HVAC and heat
7,400 VAtwo-pole breakers sized from the unit nameplate

One line for the file or the vendor

16 receptacles, 600 W lights, 2 ton HVAC + 5 kW heat, 2 dedicated: 5 20 A circuits, 15880 VA, 60 A feeder at 208 V, 12-space panel.

Keep this result, or have it priced

One email with what you asked for. No list, no newsletter.

How it is figured

  • Receptacles at 180 VA each (NEC 220.14(I)) on 20 A circuits loaded to 80% (1,920 VA); lighting at 125% continuous; HVAC at about 1,200 VA per ton plus electric heat, at 125%; dedicated equipment at 1,500 VA each.
  • Feeder amps = total VA ÷ (volts × 1.732 for three phase); breaker at 125% rounded up to a standard size. Panel spaces with about 30% spare.

Sources: NEC 2020 Article 220 (branch circuit and feeder calculations), 210.11, 210.20. A planning calculator; the maker, the engineer of record, or the code official confirms the final number.

Questions people ask

Do I need a subpanel in the office?
Almost always: one feeder from the plant panel to a subpanel in the office is cheaper and neater than a dozen home runs, and the office can be moved with its panel. Modular office makers ship them pre-wired with the panel in place.

Related calculators: Office HVAC BTU, Breaker size, Wire size for amps. All calculators.