Metal buildings and structure · guide
Metal building sheeting take-off: the guide
A sheeting take-off is four numbers from the drawings turned into a bill of panels and trim. Get the slope length and the panel count right and the rest is multiplication; get the overhang wrong and every roof sheet is a foot short.
Why this number matters
The roof is the expensive mistake. A roof panel runs from the eave to the ridge along the slope, not across the plan. A 40-foot-wide gable on a 1:12 pitch has a 20-foot run and a 20-inch rise, and the slope is just over 20 feet 1 inch; add a 3-inch eave overhang and round to the cut increment and the roof sheet is 20 feet 4 inches. Forty-two of them, one per 36 inches of eave on each side, with the last one trimmed or lapped. Miss the overhang and the sheets stop short of the eave trim; miss the rise and they do not reach the ridge cap.
Walls are simpler but carry their own traps. Sidewall panels are the eave height plus the drop below the slab, one per panel width along the length. Endwall panels follow the rake, so every one is a different length; the take-off counts them and carries the total, and the endwall calculator does the schedule. The square footage is what the panel supplier quotes against and what the insulation and the fasteners are figured from.
Trim is where quotations differ. Eave trim runs both sidewalls; rake trim runs both slopes of both endwalls along the slope length; ridge cap runs the length; corner trim runs four corners at the eave height; base trim runs the perimeter. Add the openings' jamb and header trim from the door schedule and the list is complete enough to check a building package line by line.
How it is figured
- Rise = half the width × pitch ÷ 12 for a gable. Peak height = eave height + rise.
- Slope length = √(run² + rise²). Roof panel length = slope length + eave overhang, rounded up to the cut increment.
- Roof panels per side = building length ÷ panel coverage, rounded up; roof square feet = 2 × panels per side × panel width × panel length.
- Sidewall panels = length ÷ panel coverage per side at the eave height; endwall panels from the endwall calculator at the beam height, stepping up the rake.
- Trim: eave = 2 × length; rake = 4 × slope length; ridge = length; corner = 4 × eave height; base = the perimeter.
A worked example
A 40 by 60 building, 16-foot eave, 1:12 pitch, 36-inch panels, 3-inch overhangs. The peak is 17'-8", the slope is 240.8 inches, and the roof sheet is 20'-4": 21 per side, 42 in all, 2,562 square feet of roof. Twenty 16-foot sidewall panels per side, 14 endwall panels per end, and 120 feet of eave, 80 feet of rake, 60 of ridge, 64 of corner, and 200 of base trim.
The tool's starting values, and what it returns for them:
| Width by length | 40' by 60' |
| Eave height | 16'-0" |
| Pitch | 1:12 |
| Panel coverage | 36" |
| Eave and rake overhang | 3" |
| Cut increment | 1" |
| Roof panel length | 20'-4" (244") |
| Roof panels | 21 per side, 42 total |
| Roof sheeting | 2,562 sq ft |
| Peak height | 17'-8" |
| Sidewall panels | 20 per side at 16'-0", 1,920 sq ft |
| Endwall panels | 14 per end, 1,404 sq ft |
| Eave / rake / ridge trim | 120' / 80' / 60' |
| Corner / base trim | 64' / 200' |
What to take off the drawings
- Width and length out to out of the steel line, from the anchor bolt plan.
- Eave height from the top of the concrete to the top of the eave strut or the roof line, as the drawings define it.
- Roof pitch in inches per foot and the eave and rake overhangs from the roof framing plan.
- Panel coverage width from the panel profile and the mill's cut increment.
Tools: the anchor bolt plan, the roof framing plan, the panel profile sheet
Mistakes that catch people
- Taking the roof length from the plan dimension instead of the slope; on steep pitches the difference is feet.
- Forgetting the eave overhang, or adding the rake overhang to the panel length when it only adds to the count.
- Counting sidewall panels from the length between columns rather than out to out of the steel.
- Treating the endwall as the same length as the sidewall; it is a schedule, not one number.
- Deducting doors and windows from a budget take-off, then finding the openings' trim was never added.
Rules of thumb
- Roof sheet = slope + overhang, rounded up. Slope at 1:12 is about 0.35% longer than the run; at 4:12 it is 5.4% longer.
- One roof panel per 36 inches of length per side, plus one when the length is not a multiple.
- Trim lineal feet runs close to half the roof square footage divided by 10 on a plain rectangular shell.
When to stop calculating and make a call
- Standing seam roofs, insulated panels, or panels over 40 feet long: the maker's bill of material and the shipping limits govern.
- Lean-tos, extensions, or roof steps: each is its own take-off.
- The quotation is for a re-skin of an existing building: measure the building, not the old drawings.
Questions people ask
- How is the roof panel length figured?
- The rafter slope length from the eave to the peak, plus the eave overhang measured along the slope, rounded up to the cut increment. A 40-foot-wide building on a 1:12 pitch has a 20-foot run, a 20-inch rise, and a slope just over 20 feet 1 inch, so a 3-inch overhang gives a 20-foot 4-inch roof sheet.
- Why are endwall panels different lengths?
- They run vertical and stop at the rake, so every panel is longer than the one nearer the corner. The square-cut method cuts them to the rake height at the low edge and lets the rake trim close the step; the endwall calculator shows every length and the cut list.
- Does the take-off deduct for doors and windows?
- No. It is a gross sheeting and trim count for budgeting and for checking a quotation. Framed openings add jamb and header trim and remove some panel area, and the building maker's bill of material governs the order.
- What panel width should I use?
- 36-inch coverage for PBR and R panel, the usual exposed-fastener panels on industrial buildings. Concealed-fastener standing seam panels run 24, 18, or 16 inches, and the roof count changes with them.
Standards and sources
- Metal building makers' erection manuals: roof and wall sheeting layout, overhangs, and trim
- Panel makers' profile sheets: coverage widths, lengths, and cut increments
- Line Item Supply: metal building cost per square foot
This guide and the tool are planning aids. The equipment maker, the engineer of record, the accountant, or the code official confirms the final number for your building.