Dock seal slope and taper: the guide

A dock seal is foam that the trailer squeezes against the wall. On a sloped drive the trailer does not arrive square, so a straight seal is crushed at one end and barely touched at the other; the taper puts the foam where the trailer actually is.

Open the calculator

Why this number matters

Back a trailer down a drive that slopes toward the building and the whole trailer tilts nose-up. Its rear face, which was vertical on level ground, now leans toward the wall at the same angle as the drive. The bumpers meet it at one height, four feet off the drive, but the roof of the trailer is nine or ten feet above that, and at a 4% grade the roof is four inches closer to the wall than the bumper face. A straight side pad with ten inches of projection is compressed six inches at the bottom and ten at the top. The top of the foam is crushed flat every day, the fabric wears through within a season, and the trailer roof can touch the wall above the door before the bumpers touch anything.

The fix is older than the calculators: order the side pads thicker at the bottom than the top by the amount of the lean, so that the trailer compresses the same four to six inches top to bottom. On an inclined approach, where the drive rises toward the building, the trailer leans away and the taper runs the other way, thicker at the top. Seal makers call this a tapered or wedge pad and they will build it to the inch, but they need the grade, and most order forms get a guess.

The same lean decides the bumpers and the head. If the roof leans in further than the bumpers project, no seal in the world helps; the bumpers go deeper first, or the dock gets projected, and the seal is sized from the new bumper face. At the top, a fixed head pad works only when every trailer roof clears the door head; a taller door with a mixed fleet wants a drop curtain that hangs down to meet whatever roof arrives.

How it is figured

  • Grade is the drop over the run, as a decimal: 12 inches over 600 inches is 0.02, or 2%.
  • Lean is the pad height times the grade: an 8-foot pad on a 2% decline leans 1.92 inches, rounded to the nearest half inch for the taper.
  • Bottom projection on a decline is the standard size at least 4 inches more than the bumper projection, from 10, 12, 14, 16, 18, 20, 22, and 24 inches. The top is the bottom less the taper. On an incline the thick end is the top.
  • The trailer should compress the foam between 4 and 6 inches at both ends; a warning shows when straight pads would exceed 6 at the thick end.
  • Head: a fixed pad when the lowest trailer roof clears the door head by 3 inches or more, sized in 6-inch steps to reach the tallest trailer; otherwise a drop curtain of 18 to 24 inches.
  • Wall clearance is the bumper projection less the lean of the trailer roof above the dock; when it drops below 4 inches, the tool gives the bumper projection that restores it.

A worked example

An 8 by 8 door on a 48-inch dock with 4-inch bumpers, and the drive drops 12 inches over 50 feet. That is a 2% decline, and the lean over an 8-foot pad is just under 2 inches. The pads go 10 inches at the bottom, tapered to 8 at the top, with an 18-inch head pad over 13-foot-6 trailers; the unit is 114 by 114 overall. With 4-inch bumpers the trailer roof comes within 2 inches of the wall, so the tool asks for 7-inch bumpers.

The tool's starting values, and what it returns for them:

Door8' wide by 8' high
Dock height48"
Bumper projection4"
ApproachDecline
Drop over 50'12" (2%)
Trailers12'-6" to 13'-6"
Side pad projection, bottom10"
Side pad projection, top8"
Taper2", thick end at the bottom
Head18" fixed head pad
Overall unit114" wide by 114" high, 90" inside
Compression6" at the bottom; 7.9" at the top if straight
Wall clearance with 4" bumpers1 3/4"
Bumpers needed for 4" clearance7"
  • With 4" bumpers the top of a 13'-6" trailer comes within 1 3/4" of the wall. Use 7" bumpers or a projected dock to keep 4".
  • Straight pads would compress 8" at the top, over the 6" limit; order the taper.

How to measure the grade

  1. Stand at the dock face with a string, a line level, and a 50-foot tape. Hook the string at the dock floor height on the bumper or the wall.
  2. Walk the string straight out along the path the trailer takes, 50 feet if you can, and pull it taut and level by the line level.
  3. At the far end measure from the string down to the drive. That is the drop. If the drive is above the string, the approach is inclined; measure up instead.
  4. Enter the dock height, the drop, and the run. The tool converts to the grade. Measure over the whole trailer length, not the last ten feet; the trailer's angle is set by where its axles and landing gear sit.

Tools: mason's line, line level, 50-foot tape, a helper at the far end

Mistakes that catch people

  • Guessing the grade from the look of the drive. A 2% slope is invisible to the eye and already worth 2 inches of taper; 4% looks flat and crushes the top of a straight seal.
  • Measuring the slope over the last ten feet by the wall, where the apron often flattens, when the trailer's angle comes from its full length.
  • Ordering deeper seals to fix a lean problem that belongs to the bumpers: the foam cannot hold a trailer off the wall.
  • A fixed head pad on a 9- or 10-foot door with a mixed fleet; the low trailers never touch it and the tall ones tear it.
  • Forgetting that the seal's projection moves the trailer bed out, which costs the leveler lip its purchase; projection past about 20 inches is shelter territory.

Rules of thumb

  • Lean in inches is close to one inch per percent of grade over an 8-foot pad.
  • Side pad projection: bumper projection plus about 5 inches, in standard sizes.
  • Compress the foam 4 to 6 inches, never more than about 45% of its projection.
  • Head pad for 8-foot doors on a 48-inch dock; curtain for 9 feet and up.

When to stop calculating and make a call

  • The decline is past 10%: the drainage, the leveler, the restraint, and the bumpers all change together, and a projected dock is usually the answer.
  • Projection would exceed 20 inches: a dock shelter with a canopy and curtains seals that gap better than foam.
  • Trailers taller than 13'-6", double-stacked step vans, or swing doors that must open inside the seal.

Questions people ask

Why does a sloped approach change the dock seal?
On a declined approach the trailer sits nose-high and its back leans toward the wall. The top of the trailer is closer to the building than the bumper line by the grade times the height above the bumpers, so a straight seal is over-compressed at the top. Tapered side pads, thicker at the bottom than the top by that amount, keep the compression even.
How do I measure the grade?
Hold a string level at the dock floor and run it 50 feet out along the trailer path. Measure from the string down to the ground at the far end. That drop divided by 600 inches is the grade: a 12-inch drop is 2%, an 18-inch drop is 3%.
How much projection should the side pads have?
About 5 inches more than the bumper projection on a level dock, so a 4-inch bumper takes a 10-inch pad and a 14-inch bumper takes a 20-inch pad. On a decline, project the bumpers first so the trailer roof stays at least 4 inches off the wall, then size the pads from the new bumper face.
Head pad or curtain header?
A fixed foam head pad when every trailer roof is above the door head, which is the case for 8-foot doors on a 48-inch dock. When the door is 9 feet or taller the lowest trailers sit below the door head, so a drop curtain of 18 to 24 inches hangs down to meet the roof.
Does this replace the seal maker's survey?
No. It gives the size, the taper, and the numbers to check a quotation against. The maker confirms the model, the foam, the pleats, and the mounting from the door survey.

Standards and sources

  • Dock seal makers' sizing guides: side pad projection by bumper projection, tapered pads for declined approaches, 4" to 6" compression
  • Loading dock design guides: approach grades, bumper projection, and trailer lean on declined docks
  • Line Item Supply: dock seal vs dock shelter

This guide and the tool are planning aids. The equipment maker, the engineer of record, the accountant, or the code official confirms the final number for your building.