A metal building is engineered for the loads on its order and little more. Before anyone hangs a crane, mounts solar, or sets a rooftop unit on an existing building, an engineer has to check the framing for the new load. Here is why, what the engineer needs, and what the options are when the answer is no.

Cutaway drawing of a clear-span metal building interior with tapered rigid frames and no interior columns

Representative drawing of the equipment type, not the exact configuration quoted.

Why a metal building has little reserve capacity

The efficiency of a metal building comes from designing each member for the loads it was given. Frames are tapered to match the bending in them. Purlins and girts are light cold-formed sections sized for the panels, the snow, the wind, and whatever collateral load was on the order.

That is good engineering, not a weakness. It also means there is no spare strength set aside for equipment nobody mentioned. A building ordered with no collateral load has no engineered allowance for one. A building ordered without a crane was not designed for crane loads, sideways forces, or the stiffness a crane needs.

Loads also do not stop at the member they sit on. A rooftop unit loads the purlins, which load the frames, which change the column reactions, which load the foundation. Each link has to be checked.

Isometric drawing of steel frames, purlins, girts, and cross bracing in a new building

Representative drawing of the equipment type, not the exact configuration quoted.

What an engineer needs to check the building

The more of this you can gather before you call, the shorter and cheaper the review.

  • The original building drawings: erection drawings, anchor bolt plan, and column reactions
  • The letter of certification or the calculations, which state the design loads and the code
  • The manufacturer's name and the order or job number, often on a tag or data plate fixed to a frame or an endwall column
  • Photographs of the frames, the purlins, the bracing, and the connections, with measurements of the members
  • The foundation drawings, if the new load increases the reactions
  • The new loads: weight, footprint, and exact location of each piece of equipment, and how it attaches
  • For a crane: the crane data from the crane supplier, including capacity, span, and wheel loads
  • For solar: the array layout, the weight of the system, and the attachment method
  • Any changes made since the building was built, and any visible damage or corrosion

What each kind of load does

The three common requests load the building in different ways.

How added loads act on an existing metal building
Added loadWhat it does to the buildingWhat usually gets checked
Overhead craneMoving vertical, sideways, and lengthwise forces, with stiffness requirementsFrames, columns, bracing, foundation, and drift
Solar on the roofAdded dead load, and changed wind and snow behavior at the arrayPurlins, roof panels and their attachment, frames, and the roof warranty
Rooftop unitsConcentrated loads, plus an opening in the roof for the curbPurlins at the unit, added framing under the curb, and the frames
Sprinklers, ducts, and lightingDistributed hanging load, with heavier mains at certain linesThe collateral load on the original order against what is being hung
Mezzanine tied to the buildingFloor loads into the columns, and added seismic massColumns, foundation, and bracing
Roof retrofit over the old roofAdded dead load from the new roof systemPurlins and frames for the added weight, and the attachment

Options when the building cannot take it

A failed check is not the end of the project. It changes where the load goes.

  • Reinforcement: an engineer designs added purlins, strengthened members, or added bracing, and a steel contractor installs it
  • Free-standing structures: a crane on its own columns and foundations, or an equipment platform that does not touch the building frame
  • Equipment on grade: units set on a pad outside, with ducts run through the wall
  • A different product: lighter equipment, a smaller array, or a layout that puts the load near the frames
  • A new building or an addition designed for the load from the start

Who to call

Start with the original manufacturer if you can identify it. The manufacturer has the design for your order and can often say what the building was designed for, and may be able to review the new load or supply reinforcement.

If the manufacturer cannot be identified, is no longer in business, or does not offer the service, hire an independent structural engineer licensed in your state. Without the original drawings the engineer has to measure the building and work from what is there, which takes longer. Either way, the building department may require a permit and sealed drawings for the change.

What we can and cannot supply

We do not engineer, certify, or approve existing buildings. That work belongs to the original manufacturer or to an engineer you hire, and we will not tell you a roof can carry a load.

What we can supply is the new steel once the answer is known: a new metal building or an addition engineered for the crane, the solar, or the rooftop units from the start, with the loads on the order. Freight to the job site is included in every quotation. Erection can be quoted as a separate line on request, and the foundation is by others, designed from the column reactions.

Packages are sold through contractors and erectors, so owners should bring their builder or tell us who is building it. The package builder on this site has a step for openings and loads, which is where a planned crane or rooftop unit belongs.

Questions

Can I add a crane to an existing metal building?
Only after a structural review. A building not designed for a crane usually needs reinforcement to carry one on its frames. The most reliable route is often a free-standing crane on its own columns and foundations inside the building.
Can I add solar to a metal building roof?
Possibly. An engineer has to check the purlins, the frames, and the panel attachment for the added weight and the changed wind and snow loads. Ask the roof manufacturer how the attachment affects the roof warranty before anything is clamped or fastened to it.
Can my metal building support rooftop units?
Not unless it was designed for them or an engineer has checked it. A rooftop unit is a concentrated load on light roof members and needs framing under its curb. The original drawings state whether the units were on the order.
How do I find out what loads my metal building was designed for?
Look at the original drawings and the letter of certification, which state the design loads and the code. If you do not have them, find the manufacturer's tag on the building and ask the manufacturer for the order records.
Does a metal building retrofit roof need an engineer?
A new roof system installed over the old one adds weight to framing that was designed for the original roof. An engineer should confirm the purlins and frames can carry it. The building department says whether a permit is required.
Do I need a permit to add equipment to an existing building?
The building department decides. Structural changes and new rooftop equipment commonly need a permit and may need sealed drawings. Ask before the work is scheduled.