Collateral loads: what hangs from the roof has to be on the order.

A metal building roof is designed for the loads it is told about and very little more. Collateral load is the allowance for everything permanent that hangs from the roof structure and is not part of the building. It is the input most often missing when a building is ordered.

Cutaway drawing of a clear-span metal building interior with tapered rigid frames and no interior columns

Representative drawing of the equipment type, not the exact configuration quoted.

What counts

If it is permanent, hung from or supported by the roof framing, and not part of the building package, it is collateral load.

  • Sprinkler mains and branch lines, filled with water
  • Ductwork and its insulation
  • Lighting, cable tray, conduit, and busway
  • Suspended ceilings and their framing
  • Process piping and compressed air lines
  • Unit heaters and other hung equipment
Isometric drawing of metal building roof framing with purlins and rod bracing

Representative drawing of the equipment type, not the exact configuration quoted.

Uniform and concentrated

Most collateral load is given as a uniform allowance in pounds per square foot over an area of the roof. The mechanical, electrical, and fire protection designers are the source for the right value; the specification or the structural notes usually state it.

Heavy single items are different. A sprinkler main, a large duct, a unit heater, or a rooftop unit is a concentrated load with a weight and a location, and it is given to the building engineer separately so the framing under it can be designed for it. Purlins are light members and are not meant to carry concentrated loads that were never planned.

When it is left off

A building ordered with no collateral load has no engineered capacity for one. Discovering that when the sprinkler contractor arrives means an engineering review of the existing framing and, usually, reinforcement or independent supports. It is far cheaper to carry a realistic allowance from the start, including an allowance for what the owner may add later.

Questions

What collateral load should I use?
The value for your project comes from the design team: the specification, the structural general notes, or the mechanical and fire protection engineers. We do not suggest a figure, because the right one depends on what is actually being hung.
Can loads be added to an existing metal building?
Only after an engineer has checked the existing framing for the new load. Start with the original building drawings and the manufacturer's order information, which state the loads the building was designed for.
Are solar panels a collateral load?
They are an added roof load that must be given to the building engineer, along with how they attach. On an existing building they require a structural review.