Choosing an erector: the building is only as good as its assembly.

A metal building arrives as bundles of parts and a set of drawings. The erector turns it into a structure. A good erector finishes straight, tight, and on schedule; a poor one leaves leaks and a punch list. Choosing one is a subcontract decision worth the same care as the building itself.

Isometric drawing of a metal building's rigid frames, girts, and purlins before the panels go on

Representative drawing of the equipment type, not the exact configuration quoted.

What to ask

The answers should be specific and easy to check.

  • How many buildings of this type and size have you erected, and can we call those contractors?
  • Have you erected buildings with this roof system, especially standing seam?
  • Who is the superintendent on our job, and how large is the crew?
  • What equipment will you bring, and what do you expect us to provide?
  • What is your safety program and your recent safety record?
  • What insurance do you carry, and will you name us on it?
  • Do you unload and inventory the delivery?
Isometric drawing of a steel building frame being erected with a crane on site

Representative drawing of the equipment type, not the exact configuration quoted.

Accreditation

The International Accreditation Service runs an accreditation program for metal building assemblers, AC478, which audits an erector's management, safety, and quality practices. It is the erection counterpart to AC472 for manufacturers. Some specifications require it. Where it is not required it is still a useful signal, alongside references from contractors you trust. The metal building erectors' trade association also publishes guidance on qualifications and practice.

What belongs in the erector's scope

Write these down. They are the items that otherwise become arguments.

  • Unloading, inventory against the bill of material, and reporting shortages
  • Checking anchor bolts and the foundation before steel is set
  • Temporary bracing until the structure is complete
  • Installing insulation, trim, gutters, doors, and accessories that are in the package
  • Field cutting, sealing, and touch-up
  • Cleanup, and protection of panels from metal filings that rust

Questions

Do you provide erection?
Yes, when you ask for it. We quote erection as a separate line next to the building package, priced for the job site location. If you have your own erector, the package is quoted alone.
Can my own crew erect the building?
A crew experienced in steel erection can erect a small cold-formed building from the erection drawings. Larger rigid-frame buildings need an erector with the equipment and experience for them. Steel erection has specific safety requirements that apply to whoever does the work.
Who is responsible for temporary bracing?
The erector. A partly erected metal building is not stable until its permanent bracing and enough of its framing are in place, and keeping it safe until then is part of the erector's work.