Metal building delivery and unloading: planning the truck day.

Freight to the job site is included in every quotation. Unloading is not. The trucks arrive, the driver does not unload, and what happens in the next few hours decides whether erection starts clean. This is what to expect from a metal building delivery and how to be ready for it.

Isometric drawing of a steel building frame being erected with a crane on site

Representative drawing of the equipment type, not the exact configuration quoted.

What arrives and how

A metal building ships on flatbed trailers, usually open. A small building may be a single load. A larger one arrives as several loads, sometimes on different days, and the loads are not always in erection order.

The steel is bundled and tagged. Each piece carries a mark that matches the erection drawings. The paperwork that comes with the shipment is how you account for it.

  • Primary framing: columns and rafters, loose or nested
  • Secondary framing: bundles of purlins, girts, and eave struts
  • Roof and wall panels: long, banded bundles, often on blocking
  • Trim: crated or boxed, and easy to damage
  • Hardware: boxes of bolts, fasteners, clips, sealants, and closures
  • Accessories: doors, windows, insulation, and gutters, when they are on the order
  • The bill of material: the list of every part in the building
  • Packing lists: what is on each truck
Isometric drawing of ribbed metal wall panels fastened to girts on steel columns

Representative drawing of the equipment type, not the exact configuration quoted.

Who unloads and with what equipment

The receiver unloads. That is the erector or the general contractor, and the subcontract should say which. The carrier's driver delivers the trailer and is responsible for the load until it is released. The driver does not provide equipment or labor.

Plan the equipment by task. Something has to lift the heaviest frame member off the trailer safely. Something has to lift the longest panel bundle without bending it. And there have to be enough people to rig, guide, and place each lift.

  • Lifting equipment suited to the heaviest piece on the packing list, on ground that will carry it
  • Forks long enough and wide enough to support bundles, or a spreader bar for long panel bundles
  • Slings and padding that will not cut the paint or crush panel edges
  • A crew for rigging and spotting, and one person whose only job is the paperwork
  • A plan for where each bundle goes, laid out before the first truck arrives

Site access questions to settle before shipping

A tractor and flatbed needs more room than most sites allow for. Settle these before the building ships, so the answers can go to the carrier.

  • Can a full-length tractor and flatbed reach the site, turn in, and get back out?
  • Are there weight-limited roads or bridges, low wires, or tight turns on the route?
  • Is the ground at the unloading area firm in wet weather?
  • What hours can the site receive, and are there local delivery restrictions?
  • Who is the contact on site the day of delivery, and at what phone number?
  • Is the unloading equipment and crew confirmed for that day?

Checking the shipment: shortages and damage

Check each load against its packing list as it comes off the truck. Count bundles and boxes, and look at the condition of what you can see. Write any shortage or damage on the delivery receipt before the driver leaves, and have the driver sign it. A clean signature says the load arrived complete and undamaged.

Then check the parts against the bill of material. Report anything missing or damaged in writing, with photographs, the part marks, and the packing list. The order documents state the window for reporting. Claims made after that window, or after the parts have been installed, are hard to resolve.

Do not field-repair or substitute a structural part without asking. Report it, and the manufacturer says how it is to be handled.

Storing metal building materials on site

Most finish damage on a metal building happens between the truck and the roof. Water trapped between stacked panels stains and damages the coating, and it does so quickly.

Storing metal building materials on site
MaterialHow to store itWhat to avoid
Roof and wall panelsOff the ground on blocking, with one end raised so water drainsFlat stacks, standing water, and wet bundles left banded
Panel coversA breathable cover, tented so air moves under itPlastic wrapped tight, which traps moisture
Primary framesOn blocking, clear of mud and standing waterLaying members directly on the ground
Purlins and girtsBundled on blocking, sloped to drainStacking where they collect water
TrimIn its crates, under cover, away from trafficWalking on it or stacking material on top
Hardware and sealantsIndoors or in a locked, dry containerOpen boxes left out in the weather
InsulationDry, covered, and off the groundAny wetting; wet insulation should not be installed

Before the truck day

Confirm the delivery date with us and with your crew. Have the erection drawings on site. Have the foundation complete and the anchor bolts checked, or a storage area ready if erection is not starting right away. Stage material near where it will be used, in the order it will be used.

Packages are sold through contractors and erectors, so owners should bring their builder or tell us who is receiving the building. Unloading and erection can be quoted as a separate line on request.

Questions

What should I expect on a steel building delivery?
One or more flatbed trailers carrying bundled framing, panels, crated trim, and boxed hardware, with a packing list for each load. You need equipment and a crew on site to unload. The driver delivers and does not unload.
Who is responsible for unloading a steel building?
The party receiving it, which is the erector or the general contractor. It should be written into the subcontract. Unloading is not part of the building package unless erection is quoted as a separate line and includes it.
What equipment do I need for unloading a steel building?
Equipment that can lift the heaviest piece on the packing list and support the longest panel bundle without bending it, on firm ground. The packing list and the erection drawings give the weights and lengths. Your erector chooses the equipment.
What do I do if parts are missing or damaged?
Note it on the delivery receipt before the driver leaves. Then report it to us in writing with photographs and the part marks, within the window stated on the order documents. Do not install or repair a damaged structural part before you hear back.
How long can metal building materials sit on site before erection?
As short a time as possible. Stored correctly, off the ground, sloped, and under a breathable cover, the material keeps. Panels left wet in their bundles can stain. Plan delivery close to the start of erection.
Is freight included in the metal building price?
Yes. Freight to the job site is included in every quotation. Send the job site address with your dimensions, by the package builder on this site or by phone, and the quotation is delivered to that address.