The usual split
"Usually" matters. Every item here can move, and the specification or your subcontracts decide where it lands.
| Item | Building supplier | Usually by others |
|---|---|---|
| Primary and secondary framing, bracing | Furnishes | Erector installs |
| Roof and wall panels, trim, fasteners, sealants | Furnishes | Erector installs |
| Anchor bolt plan and column reactions | Provides | Foundation engineer uses |
| Anchor bolts | On request | Concrete contractor furnishes and sets |
| Foundation design, footings, slab | Not included | Foundation engineer, concrete contractor |
| Sealed drawings and calculations | Provides where required | Building department reviews |
| Unloading and storage on site | Not included | Erector or general contractor |
| Erection | On request | Erector |
| Insulation | When ordered with the package | Erector installs; or insulation contractor |
| Framed openings | Furnishes for listed openings | Late openings are field work |
| Overhead and sectional doors | When ordered | Door contractor |
| Walk doors and windows | When ordered | Erector or glazing contractor |
| Gutters and downspouts | When ordered | Erector installs; site drainage by others |
| Roof curbs and pipe flashings | When ordered and located | Mechanical and plumbing trades |
| Crane runway beams | When the crane is on the order | Crane, rails, and electrification by the crane supplier |
| Mezzanine carried by the building | When on the order | Decking, stairs, and finishes vary |
| Touch-up paint, field cutting, sealing penetrations | Not included | Erector and the trade making the penetration |
| Special inspections and testing | Not included | Owner's testing agency |
| Sales tax and permit fees | Stated on the quotation | Owner or general contractor |
Representative drawing of the equipment type, not the exact configuration quoted.
The items that fall between bids
These are the ones we see missing most often when bids are leveled.
- Unloading: the trucks arrive and the driver does not unload
- Anchor bolts and templates
- Insulation, and who installs it
- Roof curbs and the framing under rooftop units
- Framed openings added after the order
- Closures, sealants, and trim at dissimilar materials such as masonry wainscot
- Temporary bracing during erection
- Dock equipment pits, embeds, and the steel at dock doors
How our quotation handles it
The quotation lists what is included by item and states what is by others in plain words. If you send your scope sheet, we mark it up. Because we also supply the doors, the dock equipment, and the mezzanine, several of the gaps above can be closed on the same quotation.