The process

From a sketch to steel on site: how the purchase works.

A metal building is made to order. The sequence below is the same for a rigid-frame building and a cold-formed one. Dates for each step are set by the factory on the order acknowledgment, not promised here.

Isometric drawing of a metal building's rigid frames, girts, and purlins before the panels go on

Representative drawing of the equipment type, not the exact configuration quoted.

The steps

Each step ends with something you approve before the next one starts.

  • 1. Send the dimensions, the site address, the use, and the openings. A sketch is enough.
  • 2. Quotation: the package listed by part, the design loads used, what is included, what is by others, and freight to the job site.
  • 3. Order and approval drawings: you check dimensions, openings, panels, and colors and sign them off.
  • 4. Anchor bolt plan and reactions go to your foundation engineer so the foundation can be designed and poured while the steel is made.
  • 5. Permit drawings and calculations, sealed for the project state where required.
  • 6. Fabrication, then delivery to the job site with the unloading requirements given in advance.
  • 7. Erection by your erector or general contractor from the erection drawings.
Isometric drawing of a long metal building with ribbed wall panels, overhead doors, and a navy wainscot

Representative drawing of the equipment type, not the exact configuration quoted.

What keeps a job on schedule

Decide the openings before the order. Moving a door after approval drawings means re-engineering a bay. Give the collateral loads and any crane at the start. Get the code edition and site loads from the permit office early. Have equipment and people ready to unload: the steel arrives on flatbed trucks and the driver does not unload it.

Check the delivery against the bill of material when it arrives and report shortages or damage right away, in writing, with photographs.

For contractors

On a bid project, send the drawings and the metal building specification section. We quote the package to the documents and list any clarification. After award we issue approval drawings and the anchor bolt plan as submittals, then permit drawings. See the contractors page for how the rest of the equipment scopes are handled the same way.

Questions

How long does a metal building take?
It depends on the system, the size, the season, and the factory's backlog, so we do not publish a figure. The quotation and the order acknowledgment give the dates for your building.
Can the foundation be poured before the building is ordered?
It should not be. The anchor bolt layout and column reactions come from the engineered building. Pour the foundation from the anchor bolt plan issued for your order.
Do you erect the building?
We supply the building package and we quote erection when you ask for it. Erection is priced as a separate line, so a contractor with a crew or an erector of their own can take the package alone.