Scope of supply

What ships in a metal building package, and what does not.

Most surprises on a metal building job are scope gaps: something everyone assumed was in the package. This is the list we quote to, so the building number and the contractor's number meet without a hole between them.

Isometric drawing of ribbed metal wall panels fastened to girts on steel columns

Representative drawing of the equipment type, not the exact configuration quoted.

In the package

Everything needed to stand the steel shell up on a finished foundation.

  • Primary framing: frames, columns, rafters, and endwall framing
  • Secondary framing: purlins, girts, eave struts, and flange braces
  • Wind bracing: rods, cables, or portal frames as engineered
  • Roof panels and wall panels in the profile, gauge, and color selected
  • Trim: ridge, eave, rake, corner, base, and framed-opening trim
  • Closures, sealants, and all structural bolts and panel fasteners
  • Framed openings for the doors, windows, and louvers listed on the order
  • Anchor bolt plan with column reactions
  • Erection drawings and a bill of material
Isometric drawing of two gable metal buildings with standing seam roofs

Representative drawing of the equipment type, not the exact configuration quoted.

Options added by line

These are quoted with the building when you ask for them, each as its own line.

  • Roof and wall insulation, and liner panels
  • Walk doors, windows, and overhead or sectional doors
  • Gutters and downspouts
  • Standing seam roof in place of a screw-down roof
  • Canopies, lean-tos, and overhangs
  • Translucent panels and ridge ventilation
  • Stamped drawings and calculations, where not already included

By others

The foundation is designed by a foundation engineer from the column reactions and built by the concrete contractor. Anchor bolts are usually supplied and set with the foundation. Erection is by the general contractor or an erector, or we quote it as a separate line when you ask. Permits, site work, slab, electrical, mechanical, plumbing, and interior build-out are outside the building package.

Our quotation states each of these plainly so nothing is assumed.

Questions

Are anchor bolts included?
The anchor bolt plan is included. The bolts themselves are usually furnished and set by the foundation contractor to that plan. If you want them in the package, ask and they are quoted as a line.
Is insulation included?
Only when you ask for it. Insulation depends on the energy code, the use of the building, and the roof system, so it is quoted as its own line once those are known.
Do the drawings cover the foundation?
No. The building drawings give the anchor bolt layout and the loads each column puts on the foundation. The foundation itself is a separate design by a foundation engineer.